Water on Paper: The Ken-Betwa Link and the Arithmetic of a Surplus

The Ken-Betwa link, the first of thirty river links in India’s national plan to reach construction, will cost Rs 44,605 crore at 2020-21 prices and promises irrigation for 10.62 lakh hectares of Bundelkhand and drinking water for 62 lakh people. It also floods part of the Panna Tiger Reserve, displaces Adivasi families who have spent this year in protest, and rests on a claim that the Ken has surplus water, which the government has never allowed outsiders to verify. This essay takes Bundelkhand’s need seriously and asks whether this project, judged by its full costs and its unchecked hydrology, is the right way to meet it.

In twenty years of development research, Bundelkhand has come up in almost every conversation I have had about drought, farm distress and migration. It is the region that development economists reach for when they need an example of what rainfed agriculture on poor soils, with failing monsoons and thin public investment, does to rural households. Anyone who argues about the Ken-Betwa link should begin by accepting that the need it claims to answer is real.

The government’s answer is to move water from one river basin to another. The project builds the Daudhan dam on the Ken inside the Panna Tiger Reserve in Madhya Pradesh, and a link canal of about 221 kilometres to carry water to the Betwa. The Union Cabinet approved Rs 44,605 crore for it in December 2021, with central support of Rs 39,317 crore, a 90:10 split with the states. The Prime Minister laid the foundation stone at Khajuraho on 25 December 2024, and the target date for completion is March 2030.

This essay asks whether the link is the best use of that money for Bundelkhand. It sets out what the project promises and who gets it, then examines the surplus-water claim on which everything depends, the costs the appraisal leaves out (forest, wildlife and displacement), and the cost per hectare compared with the alternatives. It gives the honest case for the project and ends with what a cost-benefit test worthy of the name would require. My position is that the project’s benefits are plausible but unverified, its largest costs are uncounted, and the people paying most of those costs are Adivasi families who will see few of the benefits.

What the project promises, and to whom

The official benefits are large. According to the National Water Development Agency, the link will irrigate 10.62 lakh hectares a year, 8.11 lakh in Madhya Pradesh and 2.51 lakh in Uttar Pradesh, supply drinking water to 62 lakh people, 41 lakh in MP and 21 lakh in UP, and generate 103 MW of hydropower and 27 MW of solar power. The irrigated districts listed by the NWDA are Chhatarpur, Tikamgarh, Panna, Damoh, Vidisha, Sagar, Datia, Raisen and Shivpuri in MP, and Jhansi, Lalitpur, Mahoba and Banda in UP.

Figure 1. Promised benefits by state.

Two features of that list matter. First, more than three-quarters of the irrigation goes to Madhya Pradesh, and Uttar Pradesh’s Bundelkhand, the part most often invoked in the project’s name, receives under a quarter. Second, the list includes Vidisha and Raisen, which lie in the upper Betwa basin outside Bundelkhand. Himanshu Thakkar of the South Asia Network on Dams, Rivers and People has argued that the detailed project report names these upper Betwa districts as primary beneficiaries. The NWDA describes the link as diverting surplus Ken water to the water-short Betwa “by substitution”: Ken water replaces Betwa water downstream so that more Betwa water can be used upstream. Whether a project of that design should be described as a Bundelkhand project is a fair question.

Even the headline number has moved. More recent figures, as compiled by India Water Portal, put the irrigation benefit at 9.08 lakh hectares across about 2,000 villages for more than seven lakh farming families. The Ministry of Jal Shakti still cites 10.62 lakh hectares. A difference of 1.5 lakh hectares is about a seventh of the benefit.

The surplus that no one can check

The whole project rests on one claim: that the Ken has more water than its own basin needs. The NWDA puts the surplus to be diverted at 1,377 million cubic metres a year. If that is right, moving it to where it can be used is efficient. If the surplus is smaller, or exists only because upstream irrigation in the Ken basin has not yet been developed, then the link takes water that the Ken’s own farmers will need later and creates a dispute for the future.

The claim has been questioned by bodies with official standing. In 2019 the CEC, the committee that advises the Supreme Court on forest and wildlife cases, called it “premature” to project a transferable surplus before irrigation options in the upper Ken basin had been exhausted, and suggested cheaper local water conservation instead. An expert panel appointed by the Supreme Court concluded that the project might be economically unviable and that the surplus assumption was unproven. Thakkar has said there is no surplus in the Ken basin at all.

The government’s reply has never been tested in public, because the basin flow data have been treated as sensitive. India Water Portal reports that independent hydrologists cannot fully verify the flow data, which has been withheld on national security grounds. Climate researchers at IIT Bombay have raised a further question. In a 2023 paper in Nature Communications, Tejasvi Chauhan, Subimal Ghosh and co-authors modelled India’s planned links and found that irrigation from transferred water could reduce mean September rainfall by up to 12 per cent in regions that are already water-stressed. Lower September rain can dry rivers after the monsoon, which is when a link is supposed to deliver. The surplus calculation treats basin rainfall as fixed. The paper’s point is that the links themselves may change it.

A Rs 44,605 crore project whose central assumption cannot be checked by anyone outside the agency that made it has not passed a cost-benefit test, whatever its benefit-cost ratio says. In development economics this is the most basic requirement of appraisal: the benefit stream must be credible to someone other than the project’s promoter.

The costs that were left out

The second problem is the costs the appraisal leaves out. Business Standard reported in 2017 that the environmental damage to the Panna Tiger Reserve was not considered as part of the cost-benefit analysis when the project was cleared.

Start with the trees, because even the count is disputed. In 2026 the Ministry of Jal Shakti told the Rajya Sabha that 17,101 trees had been identified for felling for the Daudhan dam and allied works, of which 12,404 had been felled inside the Panna Tiger Reserve. But a 2017 Forest Advisory Committee record carries the detailed project report’s estimate that 23 lakh trees would be felled, and some experts consider that an underestimate. The two figures may cover different stages and areas of the project. A difference of more than a hundredfold between two official counts still means that no one outside the ministry knows what the forest cost will be.

Figure 2. Two official counts of trees to be felled.

The forest in question is not ordinary forest. Panna lost its entire tiger population by 2009 and was restocked through a reintroduction programme; it now holds about 60 to 70 tigers. The submergence zone overlaps the Ken Gharial Sanctuary. The CEC warned of “the complete breakdown of the evolutionary processes of millions of years”. In January 2026 the National Board for Wildlife’s Standing Committee approved diverting about 272 hectares inside the Veerangana Durgavati sanctuary, one of the areas proposed to compensate for habitat lost at Panna. The compensation habitat is itself being cut.

Estimates of the submerged area vary as well. CivilsDaily’s summary puts the Panna land submerged by the dam at about 4,141 hectares. The National Herald, citing the project’s critics, puts total submergence at nearly 9,000 hectares, including about 5,800 hectares in the reserve’s core. In 2014 Business Standard reported that the proposal involved diverting 6,000 hectares of the tiger reserve, with about 80 per cent of the forest required lying inside it.

The people who pay

The third set of uncounted costs falls on people. The dam displaces villages in Chhatarpur and Panna districts, and because the project takes forest from a tiger reserve, another 12 villages are to be relocated to create compensatory habitat. CivilsDaily puts the rehabilitation process at about 1,913 families. An official review in Chhatarpur in April 2026 led to village-wise resurveys in which 3,080 families were sanctioned benefits, and 638 more afterwards. The number of affected families, like the number of trees, is still being counted while construction proceeds.

The Ministry of Jal Shakti says compensation is adequate and that most eligible families have been fully paid. Its package offers a rural plot and Rs 7 lakh, an urban plot and Rs 6.5 lakh, or a one-time payment of Rs 12.5 lakh for families that do not take a plot, with land compensated at Rs 12.5 lakh per hectare or the amount due under the 2013 land acquisition law, whichever is higher. The Ministry called allegations of non-payment “incorrect and misleading”.

The families have not accepted that account. On 8 April 2026, Adivasi women in Dhondhan staged a “chita satyagraha”, lying on funeral pyres to protest violations of the Forest Rights Act and the land acquisition law. Protests resumed in July. A fifteen-day hunger strike near Kupi village ended when police cleared the site on 19 and 20 July. A protest movement led by Adivasi women has been running since 2022. The National Herald described the tribal families as paying the cost for a river-linking dream.

The protesters’ central complaint is about land, not cash. A family whose income comes from forest produce, grazing and small plots of land under customary rights does not recover its livelihood with a one-time payment, however it is calculated. Development economics has decades of evidence from Indian dam projects, going back to the Narmada, that resettlement with cash and plots of uncertain quality leaves many displaced families poorer than before. The Ministry may be right that the money has been paid. That does not settle whether the families have been made whole.

There is also a distributional point that the aggregate numbers hide. The gains from canal irrigation accrue to whoever owns land in the command area, and they accrue in proportion to the land owned. A farmer with ten hectares in Vidisha gains ten times what a farmer with one hectare gains. The losses fall on households in the submergence and relocation zones, many of them Adivasi, whose assets are largely forest access and customary land that a cash package values poorly.

A project can pass a benefit-cost test in aggregate while moving welfare from poorer households to richer ones. Development economics has a standard answer: weight the gains and losses by income, or at least report who gains and who loses alongside the aggregate. Neither the NWDA’s summary nor the Ministry’s statements on compensation does this.

What Bundelkhand has already tried

The link is not the first large sum the Union has committed to Bundelkhand’s water problem, and the record of the last one matters for this one. In November 2009 the Cabinet approved a special drought mitigation package of Rs 7,266 crore, Rs 3,506 crore for seven districts of Uttar Pradesh and Rs 3,760 crore for six districts of Madhya Pradesh, to be spent over three years from 2009-10. The package followed an inter-ministerial team’s report, and its design was the opposite of a river link. The team recommended, as summarised in a NITI Aayog and TERI policy brief, participatory watershed management, recharge of dug wells, repair of the Bundela, Chandela and Peshwa tanks, and new farm ponds and open wells.

The money moved slowly. By August 2011, a Lok Sabha answer showed, one component had spent only Rs 214.21 crore, or 24.9 per cent, of what had been released. By 2015 total releases to both states stood at Rs 4,015.20 crore, six years into a three-year package. A 2021 government reply put releases at Rs 3,107.87 crore to Uttar Pradesh and Rs 704.5 crore to Madhya Pradesh over 2009-10 to 2018-19. A Cobrapost investigation reported by The Wire found that the package had delivered very little on the ground, with works recorded that villagers could not find.

That history cuts two ways, and both deserve weight. Supporters of the link read it as proof that decentralised works, spread across thousands of sites and run by state departments, leak and stall, and that one large dam with a central agency behind it is easier to build and to audit.

Critics read it as proof that the local route was never properly tried: a package that spent a fraction of its money through weak institutions says little about what tanks and watersheds could do if funded and monitored. Both readings agree on one thing. Bundelkhand’s water problem has been, for fifteen years, as much a problem of state capacity as of hydrology, and a dam does not fix the capacity to resettle families, settle forest rights or maintain canals.

The cost per hectare, and the alternatives

What does the project cost per unit of benefit? At Rs 44,605 crore for 10.62 lakh hectares, the link costs about Rs 4.2 lakh per hectare to be irrigated, at 2020-21 prices, before counting forest, wildlife or the full social cost of displacement. On the newer figure of 9.08 lakh hectares, it is about Rs 4.9 lakh. Spread across the “more than seven lakh farming families” the government expects to benefit, it is about Rs 6.4 lakh per family.

The obvious comparison is with the local water conservation the CEC recommended. The Union’s watershed programme, WDC-PMKSY 2.0, sanctioned 1,150 projects covering 50.55 lakh hectares at a total cost of Rs 12,388.58 crore, or about Rs 24,500 per hectare treated. Its cost norm is Rs 22,000 per hectare for plain areas. But the comparison must be made carefully. The watershed programme aims to bring only about 2.5 lakh hectares under protective irrigation out of the 49.5 lakh it treats. Measured per hectare of new irrigation alone, it costs about Rs 5 lakh, close to the link.

Figure 3. Cost per hectare, river link and watershed programme.

That result is worth stating plainly, because it cuts against a common argument of the project’s critics. Per hectare irrigated, the link is not obviously more expensive than the watershed route. The differences lie elsewhere. The watershed programme’s other benefits, soil conservation, groundwater recharge and protection for rainfed land, spread across a far larger area and many more households, and it destroys no tiger reserve.

The link’s benefits depend on a surplus no one outside government can verify, and its costs include forest, wildlife and displacement that are not in the Rs 44,605 crore. A fair comparison would put both sets of costs and benefits on the table. That comparison has not been published.

There are other alternatives too. Bundelkhand has a tradition of tanks built by the Chandela and Bundela rulers, many of them silted or encroached. Restoring them, with check dams and farm ponds, was the core of the 2009 package described above. Micro-irrigation and changes in cropping toward less water-intensive crops can raise farm incomes per unit of water. None of these is free, and none can supply drinking water to large towns as reliably as a dam. But a project appraisal that does not compare the dam with them has not asked the question the region needs answered.

The honest case for the link

The government’s case deserves to be stated fully. Bundelkhand has suffered repeated droughts, and local solutions have been tried for decades without ending the region’s water stress. Surface storage on the scale of the Daudhan dam offers something tanks and watersheds cannot: a large, regulated reservoir that can carry water across dry years and supply towns as well as fields. Drinking water for 62 lakh people is a benefit that local measures struggle to match. The hydropower and solar components add revenue. And every large water project in India’s history, from Bhakra onward, has imposed heavy local costs for regional gains that later generations have valued.

The project also has legal clearances. The Forest Advisory Committee cleared it in 2017, the National Board for Wildlife gave its approval, and the Cabinet funded it. The government has raised compensation, conducted resurveys, and in its own account paid most eligible families. By the government’s statement, spending had reached about Rs 12,445 crore by July, or 28 per cent of the estimated cost.

Two things weaken that case. The first is that the legal record is still open: a challenge to the environmental clearance is pending before the National Green Tribunal, and questions about the wildlife clearance first raised by the CEC in 2019 remain before the Supreme Court. The second is the sunk-cost problem. Each rupee spent makes the project harder to stop, which is why the question of whether the surplus exists should have been settled before construction, in public, and not left for the courts after the dam is half built.

The first of thirty

Ken-Betwa matters beyond Bundelkhand because it is the first of thirty links in the National Perspective Plan to reach construction. The government has presented it as a model. If it succeeds on its own terms, it will be used to justify links across the country, some of them far larger and in basins where the surplus claim is even more contested.

Each later link will face the same three questions this one has not answered in public: whether the donor basin has a surplus once its own future needs are counted, what the forest, wildlife and displacement costs are, and whether cheaper local measures could deliver the same water.

If Ken-Betwa sets the precedent that those questions can be answered inside the agency and argued out in court afterwards, every later link will inherit the same weakness at a larger scale. That makes the method of appraisal more important than the outcome of this one project. A precedent in which the central hydrological claim is never published, the tree count varies a hundredfold between two official documents, the compensation habitat is itself diverted, and displaced Adivasi families protest on funeral pyres while construction continues, is a poor model for twenty-nine more.

What a real cost-benefit test would require

The requirements are not exotic. They are what any appraisal manual asks for, applied without exceptions for projects of national importance.

Publish the hydrology. The flow series for the Ken and Betwa basins, the method by which the 1,377 MCM surplus was estimated, and the projections of upstream demand in the Ken basin should be released for independent review. If the surplus is real, the government loses nothing by showing it.

Count all the costs. The value of the forest, the loss to Panna’s tigers and gharials, the cost of compensatory habitat, and the full livelihood loss of displaced families should be priced and added to the Rs 44,605 crore. A benefit-cost ratio that leaves them out measures only the engineering.

Compare with the alternatives, district by district. For each irrigated district, the appraisal should show what the same money would achieve through tank restoration, watersheds and micro-irrigation, with drinking water supply costed separately.

Settle land before water. Forest Rights Act claims should be recognised and settled, and a land-for-land option offered to every displaced family that wants it, before more of the submergence area is cleared. Rehabilitation figures should be published village by village. The resurveys in Chhatarpur, which added 638 families after the first count, show that the first lists were incomplete, and there is no reason to assume the Panna and relocation-village lists are better. A family left off a list in 2026 will find it much harder to get onto one after the reservoir fills.

And let the courts finish. A project whose clearances are still under challenge before the Supreme Court and the NGT should not be presented as settled, and its spending should be paced to the outcome.

Bundelkhand needs water. That is the strongest argument for the project, and it is also why the project’s assumptions must be right. If the surplus is not there, the region will have lost a forest and its displaced families their land for a canal that runs short in dry years, which is when Bundelkhand needs it most.

Further Reading

The project

NWDA, project at a glance · Cabinet approval, December 2021 · PIB FAQs on the project, August 2026

The surplus and the costs

India Water Portal on the surplus dispute · ThePrint on the tree count · Business Standard on the cost-benefit analysis

Displacement

National Herald on tribal families · Ministry of Jal Shakti on compensation

Earlier on PolicyGrounds

An Island Off the Books · The Dal Comes by Ship · The Road That Runs Back · Reading the Centre’s Books

--

Varna is a development economist and writes at policygrounds.press.

Write a comment ...

Varna

Show your support

If you've found value in my writing, consider supporting ImpactMojo (www.impactmojo.in)—a free, open-source knowledge platform I founded to make high-quality monitoring, evaluation, and development practice resources accessible to practitioners across South Asia. Your contribution helps us keep all courses, tools, and learning materials freely available to the thousands of development professionals who can't access expensive certifications or paywalled knowledge. Every donation goes directly toward developing new content, maintaining our interactive labs, and expanding resources that bridge the gap between academic rigour and on-the-ground practice. Thank you for helping democratise development knowledge.